Overview
How we discovered our first potential customers and identified any unmet needs not yet covered by current water purification methods
Within our integrated human practices, we found that water purification plants are the best fit for our filter and aligned with our values. In the market segmentation, drinking water provisionally scored highest based on severity, regulation, gap, access and willingness to pay. The unmet need in water purification plants is that reverse osmosis only relocates trifluoroacetate (TFA), discharging the concentrate and not removing TFA. In the market identification, we show that existing destruction technologies do not meet the needs of stakeholders. By meeting with companies involved in the water purification plant infrastructure, we have included their needs in our current and future designs. Water treatment companies expressed interest in a technology once it reaches TRLThe European Commission’s 1–9 scale for how mature a technology is. 8. Our first potential customers throughout all TRLs can be found in our development roadmap. In short: our first customer is a Dutch drinking water company, approached through the KWR Water Research Institute network who have the unmet need to destroy the TFA they are currently emitting.
How we have shown that Triton is a possible, scalable and inventive product
Triton is the first proposed start-to-end and synthetic biology-based TFA removal strategy. Our intellectual properties chapter expands on this, and we’ve identified the most inventive parts as patentable, for example based on their BLAST results of <43% sequence similarity to any patented sequence. Our project design page shows that we made functionalised capture beads, an approach of generating riboswitches which already worked on PFOA and an enzyme evolution platform we demonstrated on DFA. Although we are at an early stage of development, TRLThe European Commission’s 1–9 scale for how mature a technology is. 3, we have mapped out how we can reach the whole Benelux with Triton. Experts expect TFA to be regulated in the near future, which means the reverse osmosis step our system attaches to will be widely in place. What we expect regarding budget allocation to TFA remediation is best described in our market definition where we show the TAMTotal Addressable Market, the revenue if a product served its entire global market., SAMServiceable Addressable Market, the slice of the TAM a product could realistically serve. and SOMServiceable Obtainable Market, the share of the SAM that we could realistically first obtain.. The experimental scalability requires the steps through the TRL roadmap, but we want to highlight that the materials we selected (like BC or whole cell systems) are either self-replicating or easy to produce. If we manage to walk through this roadmap, we can scale Triton across our serviceable addressable market.
How we have presented logical product development plans with achievable milestones, timelines, resources and risks
The market entry shows a six-phase roadmap which we use to develop from TRLThe European Commission’s 1–9 scale for how mature a technology is. 3 to TRL 9, each with an objective we want to achieve and a gate we have to pass. Our resources are mapped out in the cost analysis, covering both physical capital and human capital. The financial analysis converts the roadmap into a financial overview that maps the required capital at 2.6M to raise and a break-even expectation in 2033. The risk assessment covers six commercial and adoption risks, each with a mitigation. Similar to this, are the barriers to entry which cover five potential technical failures, and their fallback.
How we have outlined the skills, capabilities, and stakeholders to help us develop Triton further
Our operational plan sets out the roles and teams Triton requires, and the skills required for these roles. This led to our skill gap analysis, which we based on the Dreyfus model. For each gap, we decided whether to build, borrow or outsource a skill. In our SWOT analysis, we show the benefits of having Triton being co-developed, we identify the development partner as our most predominant stakeholder. Other relevant stakeholders included in our Entrepreneurship page are involved in regulation, water treatment or are experts on developing start-ups. In short, academic skills predominantly require advisory boards, whereas logistical and entrepreneurial skills are either borrowed or trained.
How we see the positive and negative long-term impacts of Triton
TFA is a problem that is only expected to grow. The TFA problem does not only increase in concentrations, but the observed health risks related to TFA grow as well. By removing TFA from water purification plants, we reduce the exposure to TFA for everyone attached to the plant. Fully developed, Triton also removes TFA rather than relocating it, not only removing TFA from our taps, but from the environment. Although Triton has the potential to make a positive impact, we have also taken into consideration that a solution to remove a pollutant can be cause for a delay in legislation. We elaborate more excessively on these risks in our integrated human practices page and how specific risks related to our Entrepreneurship can be found in our risk assessment. Besides that, the containment of GMOs is taken into consideration for our design, which is why we use a cell-free approach for capturing and keep the bacteria for degradation inside a closed bioreactor. Our position is that Triton addresses the circulating TFA and does not replace the need for a ban on the use of products that degrade into TFA.
Background
The TFA problem and its relevance
A study from September 2026 found that, of the 110 people tested, 100% had a measurable amount of TFA in their blood plasma with a mean concentration of 21.22 ng/mL [1]. As Triton, we find this concerning. As long as there is no ban on the use of pesticides and refrigerants that break down into TFA, the environmental levels of TFA are only predicted to increase [2]. ECHAEuropean Chemicals Agency, the EU body that assesses chemical risks and recommends regulation. has recommended the EU to include TFA on the list of chemicals toxic for reproduction [3]. According to experts, legislation is the first step to TFA-free water. We learned that for stakeholders, it is not a question of whether TFA will be banned, but when TFA will be banned. The issue is that TFA is a forever chemical, and without any action, the current TFA will circulate in the hydrosphere indefinitely whilst increasing in concentration. This is where we, as team Triton, step in.
Limitations in the current TFA strategies
After asking ourselves where to apply Triton, with the help of stakeholders, we identified water purification plants as our most suitable use case. In the current infrastructure of water purification plants, TFA can only be eliminated from drinking water using reverse osmosis (RO) [4], but with RO the contaminant TFA is only relocated. The effluent water from RO, which still contains all of the removed TFA but concentrated, is discharged back into the environment. RO only concentrates TFA 5 to 10 times. According to Bert van der Waal, professor of environmental sciences at Wageningen University, concentrations in the milligrams per litre range are ideal for further processing. Even if the RO concentrate contained TFA at the Dutch indicative drinking water value of 2.2 µg/L [5], an ideal 10× concentration would reach only 22 µg/L, which is not high enough to directly treat RO concentrate. For this reason, we explored capturing TFA.
Another limitation is that TFA concentrations can only be monitored via spot tests, which give snapshots rather than a continuous measurement. Currently available degradation strategies require harsh solvents, extremely high temperatures or both. These are either energy-intensive or require post-treatment to remove solvents before the effluent water can be discharged [6].
The specific unmet need Triton addresses
There is a need for a strategy that is capable of removing TFA from the hydrosphere. Capturing TFA is required to destroy it. The degradation of TFA, including a biosensor, are key to our system. We aim to have our degradation setup in a bioreactor, where degradation runs for three days, and a biosensor continuously indicates the state of the process.
As team Triton, we have directed our efforts towards building a platform to capture TFA from a water stream and use biosensors to monitor concentrations in a degradation reactor where our culture expresses enzymes to degrade TFA. Read more about our solution on the design page.
About Triton
As Triton, we aim to use synthetic biology to capture, degrade and sense TFA. This technology forms Triton, our approach to remove TFA. To make this vision reality, Entrepreneurship will bridge the gap between the lab bench and the application of our system. Our mission is to put an end to the TFA problem and make this forever chemical forever no more.
Market identification
Market definition
Triton’s market is not water treatment, and it is not even PFAS treatment at large. Most spendings on PFAS treatment go to adsorbents and membranes that work well on long-chain compounds. Our market is what those technologies are unable to solve: capturing and destruction of the PFAS that conventional filtration cannot retain, TFA.
Currently, degradation is expensive. The carbon–fluorine bond is the strongest single bond in organic chemistry and currently the only scalable and readily available techniques to break down TFA use brute force (processes like supercritical water oxidation, hydrothermal treatment or electrochemical oxidation), all of which demand extreme temperature, pressure or current [7]
Destruction technologies currently represent roughly a quarter of the PFAS treatment market (24.9% in 2025) and form its fastest-growing segment, with a projected CAGRCompound annual growth rate, the average year-on-year growth. of 10.1% against 7.1% for the market as a whole [8]. The market is already shifting from relocation towards destruction.
Our stakeholder interviews suggest this shift will accelerate in the coming years. Frank Schoonenberg expects regulation on the release of TFA-bearing concentrate to be put in place in the near future: utilities that currently discharge concentrate would then need to treat it. This creates high demand that does not exist today. Yet, no degradation method can currently be implemented efficiently within water filtration, a limitation confirmed independently by a second stakeholder, Bert van der Waal. Waal expects enzymatic degradation to prove the most efficient route. Harrie Timmer stated that his organisation would be open to implementing such a technology once it reaches a sufficient technological level of development.
Following successful development and validation of the technology, implementation in drinking water treatment could be achieved within approximately 10 years. The key bottlenecks are expected to be permitting and certification procedures, infrastructure constraints such as grid congestion, and implementation timelines, rather than the construction work itself. If required, some of these processes could potentially be accelerated. The implementation time for the biosensor could be faster.
Taken together, these arguments presently point to a market defined by a supply gap rather than a demand gap. The obligation to destroy TFA is highly anticipated, utilities are open to adopting a solution, and the technology to meet that obligation does not yet exist in a realistic form. An efficient, workable remediation method would not merely take share of the existing remediation market, but would enlarge it.
| Technology | Energy | Residue | Readiness |
|---|---|---|---|
| Incineration | Very high | Flue gas, HF | Deployed |
| Supercritical water oxidation | Very high | CO₂, fluoride salts | Available |
| Hydrothermal alkaline | High | Salt stream | Piloted |
| Electrochemical oxidation | High | Chlorate, perchlorate | Piloted |
| Photocatalysis | Moderate | Fluoride, short-chain organic acids | Available |
| Triton | Ambient | Oxalate, F | Lab stage |
Market segmentation
Several market segments are affected by TFA contamination. To identify the best entry market for Triton, we compared these segments against a set of weighted criteria. We weighted most heavily the factors that matter for an early-stage company: a segment that cannot adopt the technology, or has no legal obligation to act, is a weak target regardless of its size.
| Segment | Severity | Regulation | Gap | Access | Pay | Score |
| (3) | (3) | (2) | (3) | (2) | ||
| Drinking water | 10 | 10 | 9 | 8 | 7 | 8.9 |
| Industrial wastewater | 8 | 7 | 7 | 4 | 6 | 6.4 |
| Groundwater remediation | 6 | 6 | 6 | 5 | 6 | 5.8 |
| Landfill leachate | 7 | 5 | 6 | 3 | 5 | 5.2 |
Explanation of criteria and weighting
Severity (3): how much TFA is in the stream, and how much harm it causes if left untreated both to the environment it is discharged into and to the people exposed downstream. Weighted heavily because a segment where TFA is scarce or harmless is not worth treating, however easy it is to reach.
Regulation (3): legal pressure to act. Stakeholder interviews indicate that the expectation of future obligations is itself a major driver of investment in PFAS remediation. Peter Fischer (Aqualab Zuid) put it directly: “It’s not a question of if, it’s a question of when”, noting that for PFOA (the first regulated PFAS) the process took five years. Sidsel Dyekjær, senior advisor on EU legislation, described the likely mechanism: “One thing I could foresee happening is that TFA is included in the total PFAS amount and the values of the upper limit of PFAS will go down.” Weighted heavily because a segment with no obligation to act will not buy, whatever the scale of its contamination.
Gap (2): inadequacy of the solution currently in place. Segment already served adequately is not available to us.
Access (3): The ease of reaching the customer and entrance into the respective market.
Pay (2): Willingness and ability to pay for a new treatment step.
Drinking water production scores highest, and the wider market data point the same way: water treatment systems account for 68.2% of the PFAS treatment market by technology, and the municipal segment for 59.8% by end use [8]. Industrial wastewater has higher TFA concentrations, but is considerably harder for us to reach. This sector is fragmented across hundreds of individual sites with no collective research route in. Additionally, dischargers have little incentive to document their own emissions. Drinking water combines strong regulatory pressure and a treatment chain that can at best separate TFA, but never destroy it. Furthermore, it is a sector that we can approach from Wageningen.
Market sizing
TAMTotal Addressable Market, the revenue if a product served its entire global market. is a metric that measures the total revenue of the market if it were entirely captured. Here, that is identified as all water requiring PFAS treatment globally, evaluated to be 2.5 billion EUR in 2025, and predicted to reach 4.3 billion EUR by 2033, with a CAGRCompound annual growth rate, the average year-on-year growth. of 7.1% [8]. Since our unique product is our enzymatic degradation, and reverse osmosis can still be deployed to remove TFA, we scaled down the degradation segment of this market at 24.9% resulting in a TAM of 706M EUR.
SAMServiceable Addressable Market, the slice of the TAM a product could realistically serve. is the portion of the TAM that our product can serve. We funnel the TAM to the SAM based on the following criteria: placement (residual streams, where a contained GMOGenetically modified organism. is permissible), predicted legal pressure, and geography. Based on this, the Benelux municipal drinking water residual streams, which carry ultra-short-chain PFAS, were selected.
Europe is the second-largest regional market after North America, and the one under the sharpest legislative pressure [8]. The Drinking Water Directive (EU) 2020/2184 became enforceable on 12 January 2026, setting parametric values of 0.5 µg/L for total PFAS and 0.1 µg/L for the sum of twenty named PFAS [14]. TFA is not among those twenty, yet it falls within “total PFAS” under the Organisation for Economic Co-operation and Development (OECD) definition and is typically the largest PFAS contributor by mass in European water [15]. In June 2026, the ECHA Committee for Risk Assessment concluded that TFA warrants classification as toxic to reproduction (category 1B) [3], and made it the first substance ever recommended as persistent, mobile and toxic (PMT) and very persistent, very mobile (vPvM).
Within Europe, the Benelux is a region containing the Netherlands, Belgium and Luxembourg. The Netherlands and Wallonia are among the few authorities to have set a TFA-specific drinking water guideline at all, at 2.2 µg/L, where no EU-wide value yet exists. All three countries heavily rely on the Rhine and Meuse rivers, and therefore share contamination and regulatory profiles.
To quantify the size of our SAM, we take the European share of the global PFAS market (29% [8]) and estimate the Benelux share of this would be 6.7% based on population. We then further narrow the scope by only considering the destruction market that accounts for approximately 10.1% of the total TAM [8]. Thus by 2033, our SAM is approximated at 27 million EUR.
SOMServiceable Obtainable Market, the share of the SAM that we could realistically first obtain. is the share of the SAM that we could realistically first obtain. In the Netherlands, 10 purification companies alone produce roughly 1.2 billion m3 of drinking water annually for the whole country. Based on our SAM estimation and on the contributed population of the Netherlands (~60%), we estimate our SOM to be 9.7 million EUR. We can first aim to partner with one or more of these companies. Vewin has indicated that Dutch water treatment companies will consider implementing the degradation method at pilot scale, but only for technologies close to being market ready.
Market entry
Entry principle
For Triton to reach the market, the three components must first be completed in the lab. We then propose to co-develop a validated system with a Dutch drinking water company. In this co-development agreement, we would focus on the binding protein that captures TFA, the enzymes that degrade it, and the sensitivity of the biosensor, while the water company steers the work towards something feasible in their own facilities, and finding a way of using Triton to treat the concentrate streams their existing filtration already produces. A successful pilot installation becomes the reference case that opens the rest of the SAMServiceable Addressable Market, the slice of the TAM a product could realistically serve..
Technology readiness
We anchor the roadmap to TRLThe European Commission’s 1–9 scale for how mature a technology is., used by the European Commission and the EICEuropean Innovation Council, the EU’s programme for funding high-risk innovation. [16].
Triton currently sits at TRL 3. We have been able to shape and functionalise bacterial cellulose with proteins. A riboswitch has also been developed to detect PFOA. A platform to evolve enzymes for improved degradation of ultra-short-chain fluorinated compounds has been produced, as well as an in silico method to generate riboswitch candidates specific for ultra-short-chain as well as other PFAS compounds.
| Phase | TRL | Objective | Gate to pass |
|---|---|---|---|
| 1. Lab development | 3 4 | Complete all three components: a protein that binds TFA, bacteria that fully defluorinate it, and a biosensor that quantifies it | Capture, destruction and detection each demonstrated separately |
| 2. Component validation | 4 5 | Integrate the three into one flow-through system; throughput, bead capacity and regeneration, reactor stability, sensor calibration | The three steps working in sequence on synthetic concentrate |
| 3. Pilot in real water | 5 6 | Co-development with a Dutch utility on a concentrate side stream | Removal efficiency in a real matrix |
| 4. Demonstration | 6 7 | Full-scale module at one production location; cost per m3, replacement cycle, compliance dossier | Reference installation and verified economics |
| 5. First commercial supply | 7 8 | Convert the pilot partner into a paying customer; bead manufacture and servicing model | A signed supply contract |
| 6. SAM expansion | 8 9 | Remaining Dutch utilities, then the wider Benelux; additional PFAS alongside TFA | Repeat installations without co-development |
Phase 1: Lab development (TRL 3 4)
Fulfil three parallel objectives: A binding protein with sufficient affinity and specificity for TFA to concentrate it from a water stream. Bacterial strains carrying enzymes that remove all three fluorines in TFA (developed using our evolution platform). Phase 1 also entails development of a biosensor with the sensitivity to quantify TFA without producing signal from other PFAS, extending the riboswitch work from PFOA to ultra-short-chain compounds.
Phase 2: Component validation (TRL 4 5)
Integrate the three results into one system. Gain information on: binding capacity per litre of bead volume; how many times the beads can be regenerated; bacterial activity and stability in the reactor over time; sensor calibration and drift; and a containment design showing that the bacteria remain inside the reactor and never enter the water. Test first on synthetic concentrate, then on a real side-stream sample obtained from a utility, which has already been supplied to us by Bodembeheer Nederland.
Phase 3: Pilot and co-development (TRL 5 6)
This is the core of our entry strategy. We partner with one Dutch drinking water utility and develop the system with them. Unproven technology is meant to enter this sector as pre-competitive collective research via KWRKWR Water Research Institute, a centralised knowledge institute on water related innovations. A technology gets assessed there in front of the whole membership. Our institutional position helps: KWR coordinates the programme, and Wageningen partakes in the same research network. Co-development allows us to work directly with our customer and allows them to influence the specification.
We pilot on-site, on concentrate from reverse osmosis brine or regeneration eluate, so transport costs for the waste stream are negligible, and no engineered organism goes near the potable line.
Phase 4: Demonstration (TRL 6 7)
A full-scale module at one production/utility location. Operations should produce a cost per m3 that can be compared against alternative capturing and destruction approaches, and a compliance dossier covering discharge consent, bacterial containment, and the sensor record as an auditable measure of how much TFA entered and how much remained. In this way, we have the information needed for SAMServiceable Addressable Market, the slice of the TAM a product could realistically serve. entry.
Phase 5: First commercial supply (TRL 7 8)
The pilot partner becomes the first paying customer. The commercial model is consumable supply and servicing rather than one-off capital sale, and each of the three components contributes:
Beads: A replaceable medium, supplied on a regeneration and replacement cycle. These can be loaded into vessels of the kind utilities already operate, so capture adds little new capital.
Bioreactor: The vessel is a genuine capital item, but the bacterial culture expressing our dehalogenase inside it is maintained under a service contract, reseeding, monitoring and strain updates. Unlike a spent adsorbent, a culture renews itself as long as it is serviced, so the recurring revenue is the service rather than the replacement.
Biosensor. Supplied with consumable sensing elements and calibration, with the option of a monitoring subscription that turns the compliance record into an ongoing service.
The bioreactor is the one component with meaningful upfront cost to the customer. Options to reduce that barrier include leasing the vessel, or pricing per cubic metre treated so the utility pays for performance rather than equipment. Which model fits is a question we aim to answer with our future partner in Phase 3.
Phase 6: SAM expansion (TRL 8 9)
With a reference installation and verified economics, expansion runs in three widening steps:
The remaining Dutch utilities: The others, sharing a regulator and the pilot results themselves. These are sales rather than co-developments.
FlandersThe Dutch-speaking part of Belgium. and the wider Benelux: De Watergroep is the largest drinking water company in Flanders, the natural second country, already inside a prominent, long-term collective research programme with the Netherlands called Waterwijs. WalloniaThe French-speaking part of Belgium. applies the same 2.2 µg/L TFA guideline but sits outside the collective, making it a separate conversation supported by the shared regulatory position.
Barriers to entry
Capture fails. A binding protein with insufficient affinity or specificity for TFA acts as a bottleneck for everything downstream. Could be mitigated by using platforms like KWR to find alternatives for capturing and continuing to degradation.
Degradation fails. Unable to produce enzymes that remove all three fluorines. Could be mitigated by pivoting to the evolution of a broader range of dehalogenases, including a TFA active dehalogenase that has been published in Copenhagen [17]. Our platform has proven to evolve higher activity.
GMO containment rejected by the sector. The architecture of the enclosed system mitigates this: the bacteria are confined to a closed bioreactor and never enter the water. Cell-free enzyme immobilisation could act as an alternative if a regulator requires it.
No utility will co-develop. While stakeholder interviews with Vewin and others suggest otherwise, later validation interviews in Phases 1–2 may yield a different result. In that case, we present a utility with a more complete project and request to pilot with them.
A competitor demonstrates enzymatic defluorination of short-chain PFAS first. Our asset is the product pipeline, not the specific enzymes per se. We file on sequences as they emerge and continue improving them toward industrial scale.
Cost analysis
Costs were built in the order: investment costs, equipment costs, production costs split into variable and fixed, and capital costs. All numbers are in constant 2026 euros. Production costs are quoted at the modelled steady state of fourteen paying sites and twenty-four monitored sites; per-site numbers follow by division.
There is no legal obligation for drinking water companies to pay for the destruction of TFA. However, based on our stakeholder analysis, we anticipate that disposing of a concentrated TFA waste stream into the environment will no longer be allowed. Dutch drinking water companies would then be obligated to remove TFA from concentrated streams such as RO concentrate. Aqualab Zuid, the laboratory serving several of these companies, covers 410 billion litres of drinking water a year, which is around one third of the Dutch total. We assume that share is exactly one third, which puts national production at about 1,230 billion litres, or 1,230 million m³ a year. A production site runs about 10 million m³ a year, so the country has about 123 production sites. We assume 35% of them run reverse osmosis or another advanced treatment step, which gives 43 addressable sites, and that we serve a third of those. The fourteen paying sites are those installations. Cost numbers were derived from literature search, calculations, interviews with stakeholders, simulation runs in Untangle.bio, or our assumptions. A complete table of the numbers used is shown at the end of this section.
Investment costs
Investment cost is the funding needed to reach an operable facility. It subdivides into purchase, direct, indirect and other costs, which together form the FCFixed Capital Costs. Start-up and validation costs and working capital are added to give the TCITotal investment costs..
Purchase costs (PC): equipment; unlisted equipment
Direct costs (DC): installation; piping; electrical; control; insulation; building; land improvement; auxiliary facilities
Indirect costs (IC): engineering; construction
Other costs (OC): land; contractor’s fee; marketing; contingency; start-up and validation; working capital
Triton buys its biomass from contract manufacturers and leases its reactors from an equipment partner, so most of these lines are zero. The only purchase cost is one functionalisation and bead-assembly line at €440,000 — a coupling vessel, wash and pack stations, and release quality control (QC) — installed in rented process space. That number is a bottom-up equipment list priced from standard chemical-engineering cost correlations and escalated on the Chemical Engineering Plant Cost Index: two 1 m³ jacketed agitated vessels, two 2 m³ buffer make-up tanks, a 3 m² wash and dewater filter, a 1 m² polish filter and two 5 kW agitators come to €118,124 of bare equipment, which at an all-in factor of 3.73 gives €440,000 [18]. A 1 m³ batch is the right size: twenty-six tonnes of assembled bead a year is twenty-six batches, one a fortnight. Installation, power, plumbing and control add €88,000 of direct cost and €8,800 of engineering, and a 20% contingency applies because the equipment price is our own build-up rather than a quotation. Fixed capital is €644,160, 1.46 times the purchase cost. Working capital is sixty days of revenue, €3,468,493 at steady state. Total investment costs are €4,112,653.
Equipment costs
Equipment is sized from the concentrate stream:
A plant delivering 10,000,000 m³/yr discharges 20% as reverse osmosis concentrate: 2,000,000 m³/yr, or 250 m³/h over 8,000 operating hours
At a ten-minute empty-bed contact time, the capture bed is 41.7 m³
On average TFA is present at 1.18 µg/L in raw water [19] and a fivefold RO concentration factor, that stream carries 11.80 kg TFA per year
Released into eluate at 10 mg/L, this is 1,180 m³/yr — a volume reduction of 1,695×
At three-day batches, the degradation reactor is 9.7 m³
The plant size, the 20% concentrate fraction and the 1.18 µg/L raw-water concentration come from the plant data established in the sections above. The fivefold concentration factor follows from the 20% and assumes complete rejection, which is why the 11.80 kg carried in the concentrate is the plant’s entire annual TFA load.
The capture bed is a fixed-bed contactor of a size a water plant installs routinely; the degradation reactor, the retention filter, the inline sensor and the controls arrive as one skid. We priced that skid twice. A 41.7 m³ bed needs a 3.66 m vessel, which the Californian drinking-water cost assessment puts at €770,601 installed [20]; a bottom-up build from standard correlations gives €519,000. We carry €590,000 as skid equipment, assembled and factory-tested, ex works, and note that site installation would add €180,000 to €295,000 [18].
Triton does not buy that skid. The equipment partner owns and supplies it, we lease it in at €75,000 per site-year and lease it on at €150,000 — the 50% margin we apply across every product. €75,000 against €590,000 of capital is 12.7% a year, and the capital recovery factor for a ten-year term at 4.32% — the cost of capital the Autoriteit Consument en Markt sets for Dutch drinking-water companies — is 12.53%, or €73,900 [21]. It is not available on a three-to-five-year lease, where published rate factors run 23% to 40%. The €75,000 we retain is margin on a bundled service in which we carry residual-value and performance risk.
In conclusion, equipment is not where this business is capital-intensive. The sizing is modest with a 41.7 m³ bed and a 9.7 m³ reactor that are ordinary objects at a plant moving ten million cubic metres a year. Our capturing module compresses the TFA from 2,000,000 m³ of concentrate into 1,180 m³ of eluate, which is the 1,695× reduction that lets a ten-cubic-metre reactor destroy a whole plant’s TFA. Because the skid is leased, none of its €590,000 enters our fixed capital; the only equipment we own is the €440,000 bead line.
Production costs
Annual production costs split into variable and fixed.
Variable: material; utilities; labour; consumables; waste; transportation; quality control; royalties
Fixed: R&D; marketing; maintenance
Not every category has a section of its own below. Transportation, quality control and royalties are small or zero, and the reactor skid lease is derived under Equipment costs. All four are carried in the totals and listed in the cost table at the end of this section.
Material costs
Beads and cells are replaced twice a year, on the six-month cycle ion-exchange resins run to. Across fourteen sites that is 23,333 kg of bacterial cellulose at €95/kg (€2,216,667), 2,707 kg of purified TFA-binding protein at €1,400/kg (€3,789,364), and 2,716 kg dry weight of degradation biocatalyst at €45/kg (€122,203) [22]. Holding the biocatalyst between batches takes 71,369 kg of glucose at €0.55/kg (€39,253). Material costs are €6,167,487 a year.
The protein figure rests on the assumption that our binder is multivalent. We assume each binding protein carries five TFA molecules, which is the design target of our evolution pipeline. A 30 kDa protein binding one TFA would hold 3.8 mg of TFA per gram and would allow the capturing bed to be loaded at 2.32 g of protein per litre.
Utilities
Zero. The utility operates the plant and the skid runs on its power and water. Triton supplies consumables and service; it does not operate anything.
Labour costs
Four salaried posts, we have assumed two scientists whose salaries are at €62,000, one field engineer at €75,000 and one commercial post at €70,000. In total, the labour costs are €269,000 a year.
Production consumable costs
Coupling the binding protein to the cellulose consumes reagents costed at €60 per kilogram of assembled bead: 26,040 kg, or €1,562,413 a year. Regenerating the bed in service consumes a caustic swing over the 1,180 m³ of eluate plus neutralisation, €4,670 per site-year or €65,383 across fourteen. Each site also carries a biomass retention membrane at €1,200 and a side-stream inactivation step at €2,500. Monitoring cartridges and service visits are €5,000 per monitored site, or €120,000 across twenty-four sites. The total production consumables cost is €1,799,596 per year.
Waste costs
The only solid waste stream of any size is the spent bead charge. Each site’s 41.67 m³ bed is replaced twice a year, which at a hydrated bed density of about 1,000 kg/m³ is 1,166.7 tonnes across fourteen sites. The TFA it captured has been destroyed in the reactor, so the material is neither fluorinated nor hazardous and therefore needs no hazard assessment. Therefore, we have assumed a waste disposal cost of €197.50 per ton, which gives €16,458.33 per site and €230,416.67 across fourteen sites a year [23].
The other waste stream is liquid. The reactor holds 97 kg of cells for six months on a feed carrying only 10 mg/L of TFA, so maintenance carbon must be dosed, and whatever is not respired leaves with the 1,180 m³ the reactor discharges each year. We model a maintenance coefficient of 0.006 g glucose per g dry cell weight (DCW) per hour, which is where two independent measurements converge: 0.0058 for E. coli under genuine carbon starvation and 0.0070 for an aerobic culture held at near-zero growth in a retentostat [24] [25].
Maintenance substrate is respired to carbon dioxide, not excreted. Of the substrate consumed in an aerobic system, soluble microbial products account for 3.1% on glucose specifically and 3 to 15% across aerobic systems generally [26]. At 3 to 5% of a 5,098 kg feed, the effluent carries 138 to 230 mg/L of chemical oxygen demand (COD) against a typical urban consent near 125 mg/L. Across fourteen sites per year, the total waste cost is between €90,762 to €92,946.
Fixed costs
Beyond labour, the company carries €55,000 of research consumables — laboratory supplies for the four staff, separate from the production consumables costed above, which scale with sites served — €48,000 of rented bench and shared equipment, €32,000 for intellectual property and legal, €22,000 of insurance and administration and €12,000 of travel. Fixed costs are €438,000 a year.
Capital costs
The only capital is the €644,160 bead-assembly line, bought once in 2029. Expansion requires no further plant and no fleet while the skids are leased.
Conclusions
€651,257 at each of fourteen paying sites, including the €576,257 delivered cost and the €75,000 skid lease, and €5,000 at each of twenty-four monitored sites add to a total variable cost of €9,237,580. Fixed costs are €438,000 per year. The total production costs, which are calculated by adding total variable costs and total fixed costs, are €9,675,580.
Investment and production costs of Triton
Input parameters for risk analysis
Financial analysis
Using the cost analysis and the time planning, we performed a financial analysis regarding the investability of our company. To do so, we performed a cash flow analysis and calculated the NPVNet present value, today’s worth of future cash flows.. The cash flow analysis reveals how money flows in and out of the company over time. The NPV reveals whether the investment is worth pursuing by comparing the value of future profits to the initial investment. These future profits are discounted for inflation.
Our model runs from 2027, the year the company is founded, to 2045. The first four years (2027–2030) are development years: Triton carries costs but makes no sales, while the technology advances from TRL 3 to TRL 8. Sales start in 2031, and our SOMServiceable Obtainable Market, the share of the SAM that we could realistically first obtain. increases over five years (10%, 25%, 50%, 75%, 100%) as production capacity and market access grow. At 100% SOM we serve 10 treatment sites, each generating €1,490,000 per year, giving €14.9 million of annual revenue in the first sales year. The inflow of money increases over time: initially because of the ramp in production capabilities, later because the PFAS destruction market itself grows at 10.1% annually [8]. The outflow of money also increases over time. Our variable costs of €651,257 per site grow at the same 10.1% as revenue, so the margin per site stays constant, while our fixed costs of €438,000 per year rise with an assumed inflation of 2%. On top of these, the model includes a one-off fixed capital investment of €1,224,520 for the bead-assembly line in 2029, and working capital equal to 60 receivable days on the yearly increase in sales. Co-development income of €180,000 in 2029 and €240,000 in 2030 partly offsets the development phase. Our annual cash flow turns positive in 2031, the first year of sales.
The cumulative cash flow reaches its deepest point in 2030 at −€2,609,784, which is the funding we must raise before the company sustains itself. From 2033 onwards the cumulative cash flow is positive, meaning all earlier losses have been earned back in the third year of sales. To discount the cash flows, a RCCReal cost of capital, the inflation-adjusted return investors require. of 10% was used, in line with investments in the biotechnological sector. The discounted cash flowA financial valuation method that estimates the present value of an investment, company, or project by discounting its expected future cash flows using a chosen discount rate. (DCFDiscounted value of an investment based on expected future cash flows.) was calculated by , where t refers to the time passed since the start of the company. The net present value was calculated as the sum of the discounted cash flows over the model horizon, with the investment costs already contained within those cash flows. In our case, the NPV was €58,160,344, and the discounted payback year is likewise 2033, suggesting that the investment is worth pursuing.
Cash flow projections
Cash flow Assumptions Market sizing SOM cross-check Cost burden Sources
SWOT analysis
| Strengths | Weaknesses |
|---|---|
|
|
| Opportunities | Threats |
|
|
Strategic decisions based on our SWOT analysis
Our core strength is our internal knowledge of TFA remediation through synthetic biology. To secure that knowledge through the start-up phase we uphold our affiliation with Wageningen University and its networks, including relations with StartHub and an advisory board.
GMO regulation is a threat to deployment, so we designed Triton to keep GMOs contained. This led to the development of cell-free capture which makes it easier to deploy under current regulations.
Developing Triton from TRL 3 needs financing and experience at the point of implementation. This is why we co-develop with partners throughout the TRL ladder.
Risk assessment
| Type | Description | Solution |
|---|---|---|
| Cost | The beads + reverse osmosis will be very expensive. | By investing in developing a strong production process, we will make the production of our product as cheap as possible. Regulations that limit the amount of TFA in the environment are expected in the near future. When these regulations are in place, the capital required to remove TFA will become available. |
| Trust | Companies might prefer to work together with an established company rather than a group of students. | We have an elaborate business plan, so it is clear where we are spending our resources to develop our product. Also, we work together with professionals from academia and industry, which can back our claims and make sure that the process is actually feasible. |
| Effectiveness | The effectiveness of the degradation is lower than expected | We will invest in research and development to increase the efficiency. We have developed a platform for evolution towards degrading TFA efficiently, so using this platform should allow for more effective degradation in the future. |
| Regulations | Regulations might not allow for engineered proteins or enzymes | Based on discussions with policymakers, our solution can be implementable and stay within current and future legislations. However, we will keep a close eye on the regulations to make sure that we will comply, also in the future. |
| Scaling | We might not be able to scale up the production of beads to the point where it can be used by water filtration companies | We will co-create with industry professionals to scale up our production pipeline. So even if our own knowledge falls short, we can rely on their expertise to make sure that the process is scaled accordingly. |
| Catch 22 | Companies might only be interested in implementing our solution once it is proven to work on a large scale due to the potential downsides if the solution does not work. If all companies think like this, we cannot implement our solution. | If the company uses RO already, the risk becomes a lot less severe. These companies can still get the drinking water out of their plants, but might just store their effluent water a bit longer so the TFA in it can be degraded. |
Operational plan
Product implementation description
As Triton, we are developing a way to degrade TFA. When a water filtration company buys our degradation method, the first thing is the bioreactor installation. We lease the bioreactor, so there is no big upfront investment. The number and size of bioreactors to be implemented will need to be agreed upon with the specific water filtration plant. When implementing the solution, we will lease a bioreactor from a company. At TRL7, we can start talking to companies that offer this service to determine the best deal we can get for this.
Before degradation, a concentration step is required. Initial concentration can be achieved via reverse osmosis, ion-exchange resin, filtration based on a binding protein, or possibly a novel method. Here we implement our capturing beads with binding proteins. The resulting concentrate is used as the input stream into the bioreactor. A small output stream from the bioreactor is connected to the biosensor. This output stream is collected and autoclaved by us to comply with GMO regulations. The main output stream of the bioreactor discharges into the environment, with a filter to retain GMO material. Our full strategy can be found on our biosafety chapter. Although our degradation process produces very low fluoride concentrations, and 25 mg/L of fluoride is allowed in the Netherlands, it is worth considering crystallising the fluoride in the reactor [27].
After installation, the concentrate and the degrading E. coli are added. The process can then be run in batch for 3 days. After this, the TFA levels can be measured using LC-MS and if the level is sufficiently low, the effluent water is discharged into the environment. The bioreactor can then start a new batch.
A maintenance team receives information from the biosensor and is ready to respond to either a biosensor-detected disruption or a call from the facility. They also maintain the bioreactor. After running for 6 months, the E. coli cells are replaced.
Organisation and growth phases
Triton will be a company with few employees: the bioreactor is leased from an equipment partner and the utility operates the plant. The company grows in three phases that follow the TRL-based roadmap [16], and each phase starts when its gate in Table 3 is passed.
| Phase | Years, TRL | Own team | Outsourced or borrowed |
|---|---|---|---|
| 1. Founding | 2027-2028, TRL 3-5 | WUR iGEM team | Advisory board, connections through WUR |
| 2. Pilot | 2029-2030, TRL 5-7 | WUR iGEM team, process and field engineers, small marketing & sales team | Equipment partner, legal advice |
| 3. Commercial | 2031-2036, TRL 8-9 | Executive board, broadening the marketing & sales team | Service visits, waste handling, patent attorney, accountant |
Intellectual property protection
We plan to register a company through the KVKKamer van Koophandel, the Dutch Chamber of Commerce so that we can continue developing our products and operate as a business entity. Intellectual property protection is key to our success as a small business. From the course Intellectual Property Rights (LAW-32306) offered by WUR and consultation with Carla Kalkhoven from the WUR’s Knowledge Transfer Office (KTO), we have learned about the patentability of an invention and, more importantly, the responsibilities that come with patent protection.
To be patentable, an invention must be novel, involve an inventive step, and be susceptible to industrial application (European Patent Convention, 1973, art. 52). In addition, the Convention explicitly excludes certain subject matter from patentability: discoveries, scientific theories, mathematical methods, computer programs “as such” (art. 52(2)), as well as plant and animal varieties and biological processes for their production (art. 53(b)). Microbiological processes and their products, however, remain patentable (art. 53(b)). These requirements rule out the patentability of the microorganism used to make the biosensor and degradation enzymes, as they belong to prior art and are thus not novel. The software that we have developed to guide the design of riboswitches and degradation enzymes is also not patentable because its source code is deposited in the iGEM GitLab. However, because the source codes are our creative work, they will be protected by copyright. Nevertheless, the riboswitches and degradation enzymes that we develop will be patentable. We ran a protein BLASTBasic Local Alignment Search Tool, a programme that compares DNA or protein sequences against databases finding similar sequences using our degradation enzyme, DAR3835 and H1_ML, against the patented protein sequences (pataa) database. The highest percent identity was only 43.30 with sequence 177248 from the patent US 9029636. The claims regarding the listed sequences from US 9029636 and other patents all require at least 95% sequence identity for a sequence to become an infringement. Therefore, the proteins that we will develop will be patentable under the European Patent Convention. We then ran a BLASTn with our designed riboswitches against the patent sequences (pat) database. We found that the riboswitch sequences we designed are similar to many of the sequences included in patents. This is primarily because our riboswitch sequences are locally mapped onto the reference riboswitch of Bacillus subtilis, which is cited by some of those patents. Additionally, none of the active patent claims include our riboswitch sequences. That being said, if we develop a riboswitch that can sense TFA, it will likely be patentable as it is new (not identical to natural sequences), involves an inventive step (a new TFA-binding function), and is susceptible to industrial application (can be used to detect TFA in water).
Skill gap analysis
To analyse and find the gaps in the expertise of our team, a skill gap analysis was done. Our team consists of students from different backgrounds and cultures pursuing a masters degree in Biotechnology, Plant Biotechnology or Bioinformatics. This skill gap analysis has also taken skills acquired when working in this iGEM team into account. The skill gap analysis highlights, for each step of our business development strategy, which skills are required and to what extent these skills are available in our team.
To quantify the skills, we use the Dreyfus model of skill acquisition. This is a 1-5 scale based on self-assessment and justification for this assessment. The grading is as follows:
This spider graph shows our average self-assessment, our highest self-assessment and the skill level we require within our start-up.
When:

Frank Schoonenberg
Process engineer at Vitens, the largest Dutch drinking water company
Following successful development and validation of the technology, implementation in drinking water treatment could be achieved within approximately 10 years. The key bottlenecks are expected to be permitting and certification procedures, infrastructure constraints such as grid congestion, and implementation timelines, rather than the construction work itself. If required, some of these processes could potentially be accelerated. The implementation time for the biosensor could be faster.
Why we reached out
We reached out to Frank to learn more about the logistics of drinking water companies and the techniques they use to treat water polluted with PFAS. We also wanted to know how Vitens prepares for upcoming regulations and what volumes Triton would need to handle to be implemented at scale.
Main takeaways
For PFAS, there are currently three technologies with a sufficient TRL: activated carbon, reverse osmosis (RO) and ion exchange resins. However, the resins are only at pilot scale and no ion exchange resins are certified for use in drinking water. Activated carbon does not work for TFA, so only RO and resins can be used. Both are scalable to drinking water volumes.
TFA is currently only removed as a side catch, as Vitens has split-stream RO installations. However, these were not designed with TFA in mind; removing TFA was an added benefit, not the goal of the installation.
A key limitation of RO is that part of the filtered water is discharged as concentrate, reducing the overall water recovery. Given the increasing pressure on drinking water resources in the Netherlands, this may be a significant disadvantage.
In the future, the concentrate, which is currently discharged into surface water, might also have to be treated. Treating RO concentrate could therefore be a very interesting application of Triton, as there are currently no high TRL TFA concentration solutions.
Vitens anticipates that TFA will be included in regulations in the future. The timeline is unknown, as it depends on politics. Vitens is currently writing an impact analysis on the effects of the new regulations proposed by RIVM.
The capacity of Vitens’ treatment plants is between around 1 and 27 million cubic metres of drinking water per year, depending on the size of the plant.
Reflection & integration
Frank gave us specific numbers regarding the scale-up of Triton, which we deemed to unrealistic for Triton. Fortunately, he pointed us to a viable alternative: RO concentrate. To help drinking water companies comply with upcoming regulations, we decided to focus on RO concentrate and rely on RO to develop Triton.